How to buy and start a soybean processing line

step-by-step guide from Bronto

Own soybean processing plant is a highly profitable business that allows you to obtain popular products: high-protein cake and soybean oil. However, launching such production raises many questions for entrepreneurs.

What does the purchasing process look like? Who is responsible for installation? What does the term “turnkey” really mean? In this article, we analyze each stage in detail and frankly – from the first call to the line reaching maximum productivity.

Soybean processing line diagram

 

We adapt our technological scheme to your conditions.

 

We manufacture soybean processing lines:

Parameter Value
Line productivity from 24 t/day 
Installed capacity from 145 kW
Products cake, oil, full-fat soybeans
Oil content of cake 7-8%
Oil cake output up to 20 t/day
Oil output up to 3.8 t/day

 

Project approval

Buying a soybean processing line from Bronto always starts with a thorough analysis of your needs.

Before signing the contract, we consistently agree on 11 key parameters:

1. Required line performance.

2. Raw material parameters (input quality of beans).

3. Finished product parameters (requirements for cake and oil).

4. Conditions for placing the line – area and height of premises, supplied electrical power, availability of access roads, storage areas for raw materials and finished products.

5. Graphic layout of the line for specific customer conditions.

6. List of equipment required for full implementation of the project.

7. Machine manufacturing terms.

8. Terms of delivery of equipment to the future production site.

9. Terms of installation.

10. Terms of commissioning.

11. Terms of payment.

Adaptation of the scheme

Once all the basic parameters have been agreed upon, we move on to the practical planning of the future workshop. At this stage, together with the customer, we work out in detail:

  • Optimal placement of production equipment in the existing premises;
  • Location and areas for warehouses of raw materials and finished products;
  • Convenient access roads for freight transport.

Based on this data, our engineers develop the final layout solution.

Why is the layout the main document at the start? It is it that allows you to create an accurate, verified list of equipment necessary for the implementation of your project. The resulting list is the only starting point for an accurate calculation of the cost of the line and forecasting the timing of its manufacture.

Only after this stage does the project move into a transparent financial plane. We provide the customer with a full commercial offer with fixed prices and terms for each unit of equipment, protecting you from hidden payments or sudden price increases during the production process.

Equipment manufacturing

After all the details are agreed, a contract is signed.

We launch the production of equipment, ensure its delivery, and after the installation is complete, we connect, configure, and start the line.

What do we mean by "turnkey"?

When customers ask about a turnkey line, everyone puts their own meaning into it. Our position is clear:

Bronto’s turnkey line is a complete set of technological equipment that is guaranteed to process soybeans into high-quality meal and oil.

However, each soybean processor has its own unique conditions: features of raw material acceptance, logistics inside the warehouse, storage tanks, specifics of the premises, etc. Therefore, we do not offer a “blind” standard solution. We adapt our equipment to your real conditions using an individual Graphic Layout. This allows you to clearly see how the line integrates into your business.

Where does the line begin?

Depending on the technical specifications and existing infrastructure, we can start designing the line from different points:

  • A dump pit (for receiving raw materials from vehicles);
  • A bunker with a feeder installed on the floor;
  • A concrete floor (direct loading).

Where does the line end?

It is not enough to know where the raw materials enter the line from – you need to clearly understand where and in what form they leave it. The final stage of the technological process is the correct, safe and logistically well-thought-out storage of finished products.

As a standard, a Bronto soybean processing line is completed with the following three nodes:

  • A storeroom for storing cake. Its usable area is usually calculated based on the norm of at least 5 days of autonomous line operation. This is an optimal buffer for uninterrupted warehouse operation.
  • Oil storage tanks. We recommend installing at least 2 tanks. At the same time, the volume of each of them should be calculated for the net shipment of exactly one oil tanker. This minimizes transport downtime and simplifies accounting.
  • A section for storing and processing of hulls and pulp. A special area for by-products of pressing and cleaning (soybean husks and sediment), which are returned to the technological process or prepared for separate sale.

Understanding the “input” and “output” points helps us create the ideal layout solution specifically for your warehouse capacity.

Equipment build

Our clients install equipment through local (regional) installation companies, using the Graphic Line Layout developed by us.

 

Why regional contractors are better

Hiring local installers is the most sensible and cost-effective solution for two reasons:

  • Economy: You do not overpay for long business trips and accommodation of an out-of-town team.
  • Legal legalization: Local companies are usually integrated into regional processes and help to go through the registration procedure and commissioning of new production with state supervisory authorities.

Bronto’s role at this stage: We do not leave you alone with the installers. If necessary, our factory provides installation supervision services – our specialist’s supervision of the correct installation of all equipment.

It is important to distinguish

Layout solution vs Enterprise project
Characteristic Layout solution (from Bronto) Enterprise project (from the project organization)
What is this? Technological diagram of the line, graphically adapted to your premises. Official documentation developed by a certified institute.
What is it for? Important for the successful physical process of soybean processing (placement of machines, conveyors). Necessary for installers and government agencies to ensure that production complies with DBN, safety standards, and passes certification.

 

Sample line graphic layout

 

Setup and start-up

After local contractors have completed the physical installation and connected the line to the ventilation and electrical network, our specialists (or official Bronto technical representatives) enter the site.

The commissioning process consists of the following steps:

  • Readiness audit: We check the condition of the equipment, the correctness of the connection and the availability of prepared raw materials.
  • Start: We conduct the first launch, bring the line to the design performance and achieve the target product quality indicators.
  • Manual: We demonstrate to the personnel of your enterprise the intricacies of settings, regulation and daily maintenance of machines.
  • Support: We provide direct contacts of our commissioning engineers for operational consultations during further operation.

Nuances of technology that you should know in advance

 1. The raw material needs to be dried.

Typically, soybeans are stored in silos at a moisture content of 12-14%. However, for maximum extrusion and pressing efficiency on our equipment, the beans must be dried to 8-9%.

Why is this important? Drying soybeans to this level allows you to increase oil yield by 5-6%, which significantly increases the margin of your production.

 

 2. Filtration or oil settling?

After mechanical pressing in screw presses, up to 3% (by weight) of solid impurities (sediment) remains in soybean oil. We offer two purification scenarios:

  • Gravity settling: The oil is clarified naturally in overflow tanks. The sediment is then removed manually. This method is suitable if the oil will be used for own needs (e.g. in animal husbandry).

 

Pre-filtration units: Mechanically purify the oil immediately after pressing. This is a must-have solution if you plan to sell the oil as a commodity, or if your line’s capacity exceeds 48 tons per day.

Guarantees, delivery times and payment terms

  • European quality: Our production is certified according to the international standard ISO 9001:2015. We guarantee uninterrupted operation of the equipment for 1 year.
  • Global support: Service and post-warranty support is provided through a network of technical representatives in 23 countries around the world.
  • Fast turnaround: We manufacture machines in series, so some of the equipment is always available in stock. The exact readiness time of the entire line is calculated after the specification is approved. Wear parts are shipped from the warehouse in 2-4 days.
  • Flexible payment: Standard terms — 50% prepayment to launch the order into production. The remaining terms are subject to negotiation. We always take into account the legislative and financial features of the country to which the equipment is supplied.

Want to see how we work?

We have already produced hundreds of plant layouts of various capacities and are ready to provide you with several ready-made options for free for review.

Our production is located in Ukraine, in the city of Cherkasy. We invite you to come to us, see the production culture with your own eyes, meet engineers and get an initial consultation.

Contact us and let us know which communication format (phone, messengers, personal meeting) is most convenient for you!

CONTACT OUR EXPERTS

Our site uses cookies.

This site uses cookies to save your preferences and personalize advertising offers. By clicking “Agree”, you consent to the use of cookies and accept our privacy policy.

Privacy Policy